Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
45.9%
OF COST SPENT
₹83.44 Cr spent
of ₹181.93 Cr sanctioned
₹98.49 Cr still to spend
on 12,112 ongoing works
Works ongoing
12,112
Open the list of these works →
Sanctioned
₹181.93 Cr
Pure scheme (wage + material)
Expenditure since inception
₹83.44 Cr
45.9% of sanction
Balance cost (unspent)
₹98.49 Cr
Wage₹62.18 Cr
Material₹36.31 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Burhanpur — Khaknar ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore