Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
35.1%
OF COST SPENT
₹89.54 L spent
of ₹2.55 Cr sanctioned
₹1.66 Cr still to spend
on 24 ongoing works
Works ongoing
24
Open the list of these works →
Sanctioned
₹2.55 Cr
Pure scheme (wage + material)
Expenditure since inception
₹89.54 L
35.1% of sanction
Balance cost (unspent)
₹1.66 Cr
Wage₹1.28 Cr
Material₹37.92 L
Trend

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By district

Amounts in ₹ Crore