Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Well
53%
OF COST SPENT
₹5.07 Cr spent
of ₹9.56 Cr sanctioned
₹4.49 Cr still to spend
on 269 ongoing works
Works ongoing
269
Open the list of these works →
Sanctioned
₹9.56 Cr
Pure scheme (wage + material)
Expenditure since inception
₹5.07 Cr
53% of sanction
Balance cost (unspent)
₹4.49 Cr
Wage₹1.36 Cr
Material₹3.13 Cr
Trend · statewide

—
—
Slowest spending this FY · worth a look
BHIND — ATER ₹15.77 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore