Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstr of Aganwadi
71.1%
OF COST SPENT
₹2.27 Cr spent
of ₹3.20 Cr sanctioned
₹92.34 L still to spend
on 40 ongoing works
Works ongoing
40
Open the list of these works →
Sanctioned
₹3.20 Cr
Pure scheme (wage + material)
Expenditure since inception
₹2.27 Cr
71.1% of sanction
Balance cost (unspent)
₹92.34 L
Wage₹36.43 L
Material₹55.91 L
Trend · statewide

—
—
Slowest spending this FY · worth a look
Dhar — Tirla −₹10.48 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type