Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
59.3%
OF COST SPENT
₹419.37 Cr spent
of ₹707.26 Cr sanctioned
₹287.89 Cr still to spend
on 4,081 ongoing works
Works ongoing
4,081
Open the list of these works →
Sanctioned
₹707.26 Cr
Pure scheme (wage + material)
Expenditure since inception
₹419.37 Cr
59.3% of sanction
Balance cost (unspent)
₹287.89 Cr
Wage₹107.71 Cr
Material₹180.18 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
ASHOK NAGAR — CHANDERI ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore