Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of Percolation Tank
45.4%
OF COST SPENT
₹4.96 Cr spent
of ₹10.92 Cr sanctioned
₹5.96 Cr still to spend
on 95 ongoing works
Works ongoing
95
Open the list of these works →
Sanctioned
₹10.92 Cr
Pure scheme (wage + material)
Expenditure since inception
₹4.96 Cr
45.4% of sanction
Balance cost (unspent)
₹5.96 Cr
Wage₹3.53 Cr
Material₹2.43 Cr
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh