Data as of 16 Oct 2026, 08:36 Admin login
FY
Reset

Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of Percolation Tank
25.4%
OF COST SPENT
₹97,903 spent
of ₹3.85 L sanctioned
₹2.87 L still to spend
on 1 ongoing works
Works ongoing
1
Open the list of these works →
Sanctioned
₹3.85 L
Pure scheme (wage + material)
Expenditure since inception
₹97,903
25.4% of sanction
Balance cost (unspent)
₹2.87 L
Wage₹2.12 L
Material₹75,489
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh