Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
43.9%
OF COST SPENT
₹9.48 Cr spent
of ₹21.59 Cr sanctioned
₹12.12 Cr still to spend
on 1,021 ongoing works
Works ongoing
1,021
Open the list of these works →
Sanctioned
₹21.59 Cr
Pure scheme (wage + material)
Expenditure since inception
₹9.48 Cr
43.9% of sanction
Balance cost (unspent)
₹12.12 Cr
Wage₹7.60 Cr
Material₹4.52 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore