Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAPlantation
27.9%
OF COST SPENT
₹2.32 Cr spent
of ₹8.31 Cr sanctioned
₹5.99 Cr still to spend
on 290 ongoing works
Works ongoing
290
Open the list of these works →
Sanctioned
₹8.31 Cr
Pure scheme (wage + material)
Expenditure since inception
₹2.32 Cr
27.9% of sanction
Balance cost (unspent)
₹5.99 Cr
Wage₹2.90 Cr
Material₹3.09 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Rewa — Gangev −₹69.63 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh