Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGAConstruction of Bund
21.2%
OF COST SPENT
₹20.45 L spent
of ₹96.61 L sanctioned
₹76.16 L still to spend
on 53 ongoing works
Works ongoing
53
Open the list of these works →
Sanctioned
₹96.61 L
Pure scheme (wage + material)
Expenditure since inception
₹20.45 L
21.2% of sanction
Balance cost (unspent)
₹76.16 L
Wage₹55.21 L
Material₹20.95 L
Trend · statewide

—
—
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Lakh