Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Well
44.6%
OF COST SPENT
₹4.07 Cr spent
of ₹9.13 Cr sanctioned
₹5.06 Cr still to spend
on 281 ongoing works
Works ongoing
281
Open the list of these works →
Sanctioned
₹9.13 Cr
Pure scheme (wage + material)
Expenditure since inception
₹4.07 Cr
44.6% of sanction
Balance cost (unspent)
₹5.06 Cr
Wage₹1.48 Cr
Material₹3.58 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore