Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGLand Development
42.4%
OF COST SPENT
₹47.90 Cr spent
of ₹112.94 Cr sanctioned
₹65.04 Cr still to spend
on 2,183 ongoing works
Works ongoing
2,183
Open the list of these works →
Sanctioned
₹112.94 Cr
Pure scheme (wage + material)
Expenditure since inception
₹47.90 Cr
42.4% of sanction
Balance cost (unspent)
₹65.04 Cr
Wage₹38.80 Cr
Material₹26.24 Cr
Trend · statewide

—
—
Slowest spending this month · worth a look
Burhanpur — Khaknar ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore