Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGFarm Pond
24%
OF COST SPENT
₹2.55 Cr spent
of ₹10.62 Cr sanctioned
₹8.07 Cr still to spend
on 299 ongoing works
Works ongoing
299
Open the list of these works →
Sanctioned
₹10.62 Cr
Pure scheme (wage + material)
Expenditure since inception
₹2.55 Cr
24% of sanction
Balance cost (unspent)
₹8.07 Cr
Wage₹6.27 Cr
Material₹1.80 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By block

Amounts in ₹ Crore