Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Check Dam/Stop Dam
68.8%
OF COST SPENT
₹1.03 Cr spent
of ₹1.49 Cr sanctioned
₹46.66 L still to spend
on 55 ongoing works
Works ongoing
55
Open the list of these works →
Sanctioned
₹1.49 Cr
Pure scheme (wage + material)
Expenditure since inception
₹1.03 Cr
68.8% of sanction
Balance cost (unspent)
₹46.66 L
Wage₹22.25 L
Material₹24.40 L
Trend · statewide

—
—
Slowest spending this month · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore