Dashboard for works

Every work in the selected area, by status, with what was sanctioned and spent. Expenditure % counts ongoing works only.

MGNREGA + VBGRAMGConstr of Cement Concrete Roads
90.5%
COMPLETED
90.5% completed
incl. physically completed · inner ring
0% spent on ongoing works
₹0 of ₹0 · outer ring
0.0% ongoing
0 works
Total works
21
Sanctioned₹8.89 L
Expenditure₹8.68 L
Spent on ongoing works0%
Closed
2
9.5% of all works
Sanctioned₹28,000
Expenditure₹0
Completed
18
85.7% of all works
Sanctioned₹7.93 L
Expenditure₹8.68 L
Physically Completed
1
4.8% of all works
Sanctioned₹68,000
Expenditure₹174
Breakdown

By district

Amounts in ₹ Lakh