Data as of 16 Oct 2026, 08:36 Admin login
FY
Reset

Dashboard for works

Every work in the selected area, by status, with what was sanctioned and spent. Expenditure % counts ongoing works only.

MGNREGA
67.1%
COMPLETED
67.1% completed
incl. physically completed · inner ring
56.1% spent on ongoing works
₹13.48 L of ₹24.02 L · outer ring
5.0% ongoing
33 works
Total works
660
Sanctioned₹6.21 Cr
Expenditure₹4.34 Cr
Spent on ongoing works56.1%
Approved
23
3.5% of all works
Sanctioned₹5.02 L
Expenditure₹0
Closed
139
21.1% of all works
Sanctioned₹34.11 L
Expenditure₹0
Completed
434
65.8% of all works
Sanctioned₹5.44 Cr
Expenditure₹4.10 Cr
Deleted
15
2.3% of all works
Sanctioned₹1.92 L
Expenditure₹0
New
7
1.1% of all works
Sanctioned₹0
Expenditure₹0
Ongoing
33
5.0% of all works
Sanctioned₹24.02 L
Expenditure₹13.48 L
Physically Completed
9
1.4% of all works
Sanctioned₹12.00 L
Expenditure₹10.61 L
Breakdown

By district

Amounts in ₹ Crore