Data as of 29 Oct 2026, 07:04 Admin login
FY
Reset

Dashboard for works

Every work in the selected area, by status, with what was sanctioned and spent. Expenditure % counts ongoing works only.

MGNREGA + VBGRAMG
83.9%
COMPLETED
83.9% completed
incl. physically completed · inner ring
41.9% spent on ongoing works
₹20.64 L of ₹49.21 L · outer ring
1.6% ongoing
16 works
Total works
1,027
Sanctioned₹7.84 Cr
Expenditure₹5.22 Cr
Spent on ongoing works41.9%
Approved
18
1.8% of all works
Sanctioned₹5.41 L
Expenditure₹0
Closed
89
8.7% of all works
Sanctioned₹54.24 L
Expenditure₹0
Completed
834
81.2% of all works
Sanctioned₹6.14 Cr
Expenditure₹4.78 Cr
Deleted
39
3.8% of all works
Sanctioned₹22.65 L
Expenditure₹7.09 L
New
3
0.3% of all works
Sanctioned₹0
Expenditure₹0
Ongoing
16
1.6% of all works
Sanctioned₹49.21 L
Expenditure₹20.64 L
Physically Completed
28
2.7% of all works
Sanctioned₹38.29 L
Expenditure₹16.34 L
Breakdown

By block

Amounts in ₹ Crore