Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Road and Culvert
52.9%
OF COST SPENT
₹97.05 L spent
of ₹1.83 Cr sanctioned
₹86.24 L still to spend
on 15 ongoing works
Works ongoing
15
Open the list of these works →
Sanctioned
₹1.83 Cr
Pure scheme (wage + material)
Expenditure since inception
₹97.05 L
52.9% of sanction
Balance cost (unspent)
₹86.24 L
Wage₹14.21 L
Material₹72.04 L
Trend · statewide

—
—
Slowest spending this week · worth a look
ASHOK NAGAR — CHANDERI ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore