Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstruction of Check Dam/Stop Dam
67.8%
OF COST SPENT
₹28.60 Cr spent
of ₹42.20 Cr sanctioned
₹13.60 Cr still to spend
on 340 ongoing works
Works ongoing
340
Open the list of these works →
Sanctioned
₹42.20 Cr
Pure scheme (wage + material)
Expenditure since inception
₹28.60 Cr
67.8% of sanction
Balance cost (unspent)
₹13.60 Cr
Wage₹8.75 Cr
Material₹4.85 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Ashok Nagar — Chanderi ₹0
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore