Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMGConstr of GP Bhawan
46.2%
OF COST SPENT
₹3.01 Cr spent
of ₹6.53 Cr sanctioned
₹3.52 Cr still to spend
on 181 ongoing works
Works ongoing
181
Open the list of these works →
Sanctioned
₹6.53 Cr
Pure scheme (wage + material)
Expenditure since inception
₹3.01 Cr
46.2% of sanction
Balance cost (unspent)
₹3.52 Cr
Wage₹1.58 Cr
Material₹1.94 Cr