Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
41.5%
OF COST SPENT
₹6.72 Cr spent
of ₹16.22 Cr sanctioned
₹9.49 Cr still to spend
on 1,236 ongoing works
Works ongoing
1,236
Open the list of these works →
Sanctioned
₹16.22 Cr
Pure scheme (wage + material)
Expenditure since inception
₹6.72 Cr
41.5% of sanction
Balance cost (unspent)
₹9.49 Cr
Wage₹5.82 Cr
Material₹3.67 Cr
Trend · statewide

—
—
Slowest spending this week · worth a look
Sidhi — Sihawal −₹1.52 Cr
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By GP

Amounts in ₹ Crore