Ongoing works

Works in progress: what they cost, what has been spent, and how fast spending is moving.

MGNREGA + VBGRAMG
47.8%
OF COST SPENT
₹58.18 Cr spent
of ₹121.67 Cr sanctioned
₹63.49 Cr still to spend
on 8,468 ongoing works
Works ongoing
8,468
Open the list of these works →
Sanctioned
₹121.67 Cr
Pure scheme (wage + material)
Expenditure since inception
₹58.18 Cr
47.8% of sanction
Balance cost (unspent)
₹63.49 Cr
Wage₹34.69 Cr
Material₹28.80 Cr
Trend · statewide

—
—
Slowest spending this quarter · worth a look
Rewa — Gangev −₹42.23 L
Top 10 new work types

Ranked by sanctioned cost

Breakdown

By new work type

Amounts in ₹ Crore